Plant Vogtle Unit 3, America’s first nuclear reactor built from scratch in more than 30 years, is now online in the State of Georgia. Built to provide clean, emissions-free energy, the plant came in $17-billion over budget and seven years late.
Contrast the above with SA’s Medupi and Kusile Projects:
In terms of budget, Medupi and Kusile had an initial budget of R79 billion and R81 billion, respectively. In 2020, the Eskom board approved budget revisions to complete the power stations, giving R145 billion for Medupi and R161.4 billion for Kusile’s build.
Medupi’s budget does not include the cost of installing the Flue Gas Desulphurisation (FGD) plant. The Medupi FGD plant is expected to cost between R35 billion and R40 billion, and will be commissioned by 2027/28. The FGD has already been installed at Kusile and is included in its budget.